HomeLocationKorea
                
 
 
 
 
 
HOME   >   Actual   >   Dismantling of Scaffolding Structures
Following are list of recent performances in Dismantling of Scaffolding Structures
 
No Project Name Duration Ordering Entity Principal
Contractor
1 Temporary safety facility in the OVERPASS section of Incheon International Airport Road 2000 New Airport Highway Co., Ltd Lotte Engineering & Construction Co., Ltd
2 Removal of (former) internal combustion power plant in Bupyeong and establishment of outdoor yard for material 2000 Korea Electric Power Corporation  
3 Production of 1st phase PC Box equipment for upper portion of PSM for the sector #8-2 of the Gyeongbu Rapid Train Railway 2000 Daewoo Construction Co., Ltd Wheesun Construction Co., Ltd
4 Removal of PSM factory facility in the sector #3 of the Gyeongbu Rapid Train Railway 2000 Korea Rail Network Authority Dongbu Corporation
5 Access facility to the bridge in construction of expansion of road between Sungjeon-Kangjin 2000~2001   Poonglim
6 Removal of obstructing structures in the Moonhak district 2001 Incheon Urban Development Corporation  
7 Dismantling of 1st phase overseas equipment for construction of upper portion of PSM 2002 Daewoo Construction Co., Ltd Wheesun Construction Co., Ltd
8 Removal of (former) medical center within the land earmarked for construction of health and environment research institute 2002 Headquarters of General Construction In Incheon Metropolitan City  
9 Dismantling of steel structure for E-MARK in Shiwha Industrial Complex 2002   Dongbu Steel Co., Ltd
 
 
BUIL Construction
Headquarters of BUIL Construction Co.,Ltd : #5 Saenaedeul-1-gil, Shimgok-dong, Seo-gu, Incheon (404-835)
TEL:032-561-8716~9   FAX:032-561-4399
Factory of BUIL Construction Co.,Ltd : #649-217 Samjon-ri, Songsan-myeon, Hwasung-gun, Gyeongi-do
TEL:063-466-0735   FAX:063-466-2229
Copyright ¨Ï Builconst All Rights Reserved.