Construction of pedestrian cross bridge in front of Shinhyundai Apt. in Gajoa-3-dong
Ordering entity Seogu Municipality, Metropolitan Incheon
Overview of the construction 2 abutments and 2 inclined roads for bridge
Duration of construction 2002.08 ~ 2003.01
Contents of construction Pedestrian cross bridge that transverses Gyeongin Highway, which was implemented by the Seogu Municipality of Incheon in order to provide convenience to the students and residents using educational facilities in Gajoa-dong. We completed steel reinforced concrete, assembly of concrete mold, pouring of concrete and installation of SHOE, burying of drainage pipe and paving of upper portion of river-crossing bridge in the foundation construction for abutments an inclined roads.
Construction of pedestrian cross bridge at Moonhyun Crossroad
Ordering entity Namgu Municipality, Metropolitan Busan
Overview of the construction Total length: 76m
Duration of construction 1998.01
Contents of construction It is a construction project implemented by the Namgu Municipality of Busan in order to ease traffic flow and safety of pedestrians around Moonhyun crossroad. We made contribution towards completion of construction of pedestrian crossing bridge at Moonhyun crossroad by newly constructing U-type gutter in order to eliminate inconveniences experienced in traffic by easing the drainage among the works involved in construction for transverse pedestrian crossing bridge and annex facilities.
 
 
BUIL Construction
Headquarters of BUIL Construction Co.,Ltd : #5 Saenaedeul-1-gil, Shimgok-dong, Seo-gu, Incheon (404-835)
TEL:032-561-8716~9   FAX:032-561-4399
Factory of BUIL Construction Co.,Ltd : #649-217 Samjon-ri, Songsan-myeon, Hwasung-gun, Gyeongi-do
TEL:063-466-0735   FAX:063-466-2229
Copyright ¨Ï Builconst All Rights Reserved.